Types of contract in project management

2001-12-29 11:33:18【作者】 畅享网 【进入论坛】
本文关键字
广告

Types of contract in project management

It is often more efficient to outsource certain project activities to external contractors than for your project team to take them on themselves. In fact, it may prove cost effective to contract out the entire contracting process itself to a dedicated contract management company.
 

Make or buy?


A make-or-buy analysis should include indirect as well as direct costs

A make-or-buy analysis is a good way of determining the cost-effectiveness, or otherwise, of producing a particular product or service within your organization. This analysis should include indirect as well as direct costs. For example, it should include the cost of managing the project's purchasing process as well as the cost of purchasing an actual product. Your make-or-buy analysis should also take into account your organization's possible future needs as well as the project's immediate ones.


Contract types

There are a number of contract types available to project managers, involving varying levels of risk for buyers and for sellers. Contract types generally fall into one of three broad categories, the risk for the buyer rising from one to the next:

  1. fixed-price or lump-sum contracts

  2. cost-reimbursable contracts

  3. unit-price contracts

Types of contract

1. Fixed-price or lump-sum contracts

This contract type involves payment of a fixed total price or lump sum for a well-defined product. Fixed-price or lump-sum contracts may also include incentives for meeting or exceeding specific targets - for example, project schedules. Risks entailed in this contract type vary according to whether the contract is

  • firm fixed price

  • fixed-price incentive

Firm fixed price (FFP) contracts, without any incentive, represent the lowest possible risk factor for the buyer. This factor increases slightly for fixed-price incentive (FPI) contracts. Conversely, FFP contracts represent the highest possible risk for the seller and slightly less risk if the contract is an FPI contract.

2. Cost-reimbursable contracts

In this type of contract, the seller is reimbursed for actual costs, both direct and indirect. Indirect costs are usually calculated as a percentage of direct costs. Cost reimbursable contracts often include incentives to be paid in the event of specific project goals, such as schedule targets or total cost being met or exceeded. Different subtypes within this contract type present different risk levels for both buyer and seller:

  • cost plus percentage of costs (CPPC) contracts entail the highest possible risk for the buyer, and the lowest possible risk for the seller

  • cost plus fixed fee (CPFF) contracts represent, for the buyer, a comparatively high risk level, and, for the seller, a comparatively low one

  • cost plus incentive fee (CPIF) contracts entail a moderate risk level for both buyer and seller


3. Unit-price contracts


Unit-price contracts carry the greatest risk for the buyer

In this contract type, the seller is paid a fixed amount for each unit of service. For example, the seller could be paid a fixed amount per hour for professional services. The number of units needed to complete the work determines the total value of the contract. This type of contract should be avoided, as it carries the greatest risk for the buyer.

如果您希望与本文章的作者或其所在机构,进一步交流,请联系:畅享网 姜小姐
jill.jiang@amt.com.cn | 021-51096826-112 | 在线联系
商蓉蓉专栏[原创]营销就是“先入为主”吗..

在激烈的竞争中要努力寻找蓝海,在进入新市场时要抢占先机,以占据有利的地位。否则错失良机,蓝海很快会变成红海。

人月神话专栏[原创]精益看板管理和敏捷软件..

我们要意识到在软件开发中的浪费没有所谓的原材料,软件开发最大的浪费就是人力资源的等待已经我们开发完成工件的返工。

郭远刚谈项目管理[原创]信息系统项目成本估算的..

1. 需求信息的复杂性。与其他有些传统项目不同,信息系统要满足的诗人的主观需要。由于人的复杂性,给信息系统带来了无数的难以确定的因素。而且,随着项目的……

中国式项目管理[原创]软件产品的生命周期

管理软件,无论规划多好,一般生存10年就不错了,随着客户个性化需求不断累积,原来的架构难以适应鲜活的业务需求。

段柯专栏[原创]诊断中小企业软件项目管..

对于企业管理,大公司有大公司的方式,小公司有小公司的方式,如果把别人的经验生搬硬套到自己身上,可能会适得其反。